RFI #114, Added Beams for Heat Recovery Coil Mechanical Pad, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #115, Cover 6” Waste Line in Dirty Wash, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #117, Foot Pedals or Wrist Blades on Sinks (Clean Wash), n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #118,Spandrel Glass in Interstitial, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #120, Masonry Insulation with Integral Vapor Barrier, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #122, SNE Catwalk Penetrations for Data, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #124, Framing Cup Anchorage in SNE Rooms, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #125, Fire Sprinkler Piping Penetrations in Beams, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #126, Can Roof Penetrations Be Cut with a Torch?, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #127, Height of Hot Water Piping in Animal Room Stud Cavities, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.