Box 12
Contains 34 Results:
RFI #39, Repair Of ARB Lightning Protection System, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #40, Painting/Material for Coiling Overhead Doors, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #41, VFD or Constant Speed on Domestic Water Pump, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #42, Turn the Water Meter Vault 90degrees, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #43, Structural Bolt Testing Procedures, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #46, Concrete & Rebar in Light Pole Bases, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #47, GHP Requests To Pour Lower Slab and Slab on Grade as One, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #48, Cubicle Room Door Hardware, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #49, Camera Pole Location East Of ISRB, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.
RFI #51, Conflict between Louver and Knock out Panel, n.d.
The second series, Construction, arrived in pieces starting in 2005 and ending in 2007. It contains all documents pertaining to the actual construction process of the Invasive Species Research Building, such as blueprints, construction schedules, and changes to the original design plan.
This series contains restricted material.