Change Order-Insulate IAV Aviary Rm Ceiling, n.d.
The second series, Construction, arrived in 2003 and contains all documents pertaining to the actual construction process of the Outdoor Pens and associated buildings, such as blueprints, construction schedules, and changes to the original design plan. These documents cover the period of 2001-2004.
Detention Pond Enlargement Study, n.d.
The second series, Construction, arrived in 2003 and contains all documents pertaining to the actual construction process of the Outdoor Pens and associated buildings, such as blueprints, construction schedules, and changes to the original design plan. These documents cover the period of 2001-2004.
Under Slab Insulation-Garage/Shop Indoor Aviary, n.d.
The second series, Construction, arrived in 2003 and contains all documents pertaining to the actual construction process of the Outdoor Pens and associated buildings, such as blueprints, construction schedules, and changes to the original design plan. These documents cover the period of 2001-2004.
WSB/ARB Electrical Shutdown To Make Hookup, n.d.
The second series, Construction, arrived in 2003 and contains all documents pertaining to the actual construction process of the Outdoor Pens and associated buildings, such as blueprints, construction schedules, and changes to the original design plan. These documents cover the period of 2001-2004.
WSB Lunchroom Incident, n.d.
The second series, Construction, arrived in 2003 and contains all documents pertaining to the actual construction process of the Outdoor Pens and associated buildings, such as blueprints, construction schedules, and changes to the original design plan. These documents cover the period of 2001-2004.
Ceiling Question in Rodent Buildings, n.d.
The second series, Construction, arrived in 2003 and contains all documents pertaining to the actual construction process of the Outdoor Pens and associated buildings, such as blueprints, construction schedules, and changes to the original design plan. These documents cover the period of 2001-2004.
RFI #041-Broom Finish on Outdoor Pen Floors, n.d.
The second series, Construction, arrived in 2003 and contains all documents pertaining to the actual construction process of the Outdoor Pens and associated buildings, such as blueprints, construction schedules, and changes to the original design plan. These documents cover the period of 2001-2004.
Submittal-Outdoor Telephone Box, n.d.
The second series, Construction, arrived in 2003 and contains all documents pertaining to the actual construction process of the Outdoor Pens and associated buildings, such as blueprints, construction schedules, and changes to the original design plan. These documents cover the period of 2001-2004.
Submittal-Hot H2O Mixing Faucet-Aviary Room-IAV, n.d.
The second series, Construction, arrived in 2003 and contains all documents pertaining to the actual construction process of the Outdoor Pens and associated buildings, such as blueprints, construction schedules, and changes to the original design plan. These documents cover the period of 2001-2004.
RFI #36-Move Electrical Backboards Outside On Outdoor Buildings, n.d.
The second series, Construction, arrived in 2003 and contains all documents pertaining to the actual construction process of the Outdoor Pens and associated buildings, such as blueprints, construction schedules, and changes to the original design plan. These documents cover the period of 2001-2004.