Box 7

 Container

Contains 55 Results:

Sketches for Reduced Floor Plan, Dec. 2008, 2008

 File — Box: 7, Folder: 21
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2008

Biosafety Cabinets, Nuaire, Models NU-425, NU-427, NU-437, n.d.

 File — Box: 7, Folder: 22
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

Redesign Meeting Minutes, n.d.

 File — Box: 7, Folder: 23
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

Size of Generator Enclosure to Include Load Bank, n.d.

 File — Box: 7, Folder: 24
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

Keenan/McCarthy/Slifer Interest in WDRB2, n.d.

 File — Box: 7, Folder: 25
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

OZ Redesign Floor Plans 9/2/08 – 9/30/08, 2008

 File — Box: 7, Folder: 26
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2008

(Redesign) – CAD Files and Collaborative Site, n.d.

 File — Box: 7, Folder: 27
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

Floor Slab Flexibility, n.d.

 File — Box: 7, Folder: 28
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

NWRC User Space Square Footage, n.d.

 File — Box: 7, Folder: 29
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

OZ Redesign Conceptual Floor Plans, 8/12/08 – 9/3/08, 2008

 File — Box: 7, Folder: 30
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2008