Box 5
Contains 74 Results:
“Biosafe Engineering” Has Purchased “WR2”, Tissue, n.d.
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
Request to OZ for Missing SFO CAD Drawings, A7.01-A8.05, 2/27/2008, 2008
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
Tradeline Biocontainment Conference April 21-22, 2008, Washington D.C.; Scottsdale 5/4-6/08, 2008
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
Bob McLean Request to Restore Tissue Culture Lab, Feb. 2008, 2008
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
GSA Prospectus Threshold Guidance, 10/24/07, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
Xnth Feedback on WDRB Design Defects, October 2007, for OZ Responses, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
Oxford Query – Existing Underground Duct Bank and Manholes, n.d.
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
Oxford Query – What Agents Will be Used in the WDRB? October 2007, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
Oxford Query – BSL-3 Ag Air Changes Versus HVAC Exhaust Velocity, October 2007, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
Oxford Query – Animal Sizes, Types, and Caging, October 2007, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.