Nine PFA Comments to Address, 5-14-07, 2007

 File — Box: 4, Folder: 61
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2007

NWRC Comments on Equipment; Tech Specs (11000’s), Drawings, and Schedule, 6/26/07, 2007

 File — Box: 4, Folder: 62
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2007

NWRC Comments on Testing, Adjusting, and Balancing, Specification 15990 7/19/07, 2007

 File — Box: 4, Folder: 63
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2007

Equipment Review, May 2007, n.d.

 File — Box: 4, Folder: 64
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

NWRC Comments on Telephone/Data Tech. Spec. 16741 and Sheets E4.02/E4.03, 6/28/07, 2007

 File — Box: 4, Folder: 65
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2007

NWRC Comments on Tissue Culture and Media Prep, 5/24/07, 2007

 File — Box: 4, Folder: 66
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2007

NWRC BSL-3 Lab Area Comments, 5/22/07, 2007

 File — Box: 4, Folder: 67
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2007

NWRC Comment on Animal Care Areas, 5/24/07, 2007

 File — Box: 4, Folder: 68
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2007

NWRC Necropsy Suite Comments, 5/15/07, 2007

 File — Box: 4, Folder: 69
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2007

NWRC Comments on Tech. Specs. 12345, 12347, 12348, &12349; 6/28/07, 2007

 File — Box: 4, Folder: 70
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2007