Building Is to Be “Fail Secure”, Not “Fail Safe”
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
NWRC Locations for Automatic Door Operators, 8/2/07, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
NWRC Comments on Door Hardware Technical Specification 08700, 6/26/07, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
Clarify Dividing Line Between BSL-3 & BSL Support at Main Lockers & Two Way Arrows, n.d.
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
NWRC Comments on Lab Gases, 15010.27, 8/8/07, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
NWRC Comments on SFO Section 9; Design, Construction, and Build Out 8/13/07, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
Required Drainage Analysis – Previous Studies Incl. Oxford Site Visit, Tom Fyffe, Hensel Phelps, 10/18/2007, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
Nine PFA Comments to Address, 5-14-07, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
NWRC Comments on Equipment; Tech Specs (11000’s), Drawings, and Schedule, 6/26/07, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.
NWRC Comments on Testing, Adjusting, and Balancing, Specification 15990 7/19/07, 2007
This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.