Toni Taylor of APHIS is Gareth Diedrick’s Representative, 2/21/03, 2003

 File — Box: 2, Folder: 51
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2003

Presentation and Approval by APHIS Administrator B. Acord, 2403 (Also R. DeHaven)

 File — Box: 2, Folder: 52
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2007 - 2009

Paraformaldehyde Decontamination for Galvanized Steel Ductwork, n.d.

 File — Box: 2, Folder: 53
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

Publication, Security for Labs Working for “select Agents”, n.d.

 File — Box: 2, Folder: 54
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

NWRC Pathogen & Security Inventory, 4/14/03, 2003

 File — Box: 2, Folder: 55
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2003

Articles on Security & Biosecurity at Lab Animal Facilities, n.d.

 File — Box: 2, Folder: 56
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

Article on “Management of a Biocontainment Research Facility”, n.d.

 File — Box: 2, Folder: 57
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

Definitions of BSL-1 Through BSL-4, n.d.

 File — Box: 2, Folder: 58
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: n.d.

Floor Plan for CSU’s BSL-3 Building, June 2001, 2001

 File — Box: 2, Folder: 59
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2001

ISRB/WDRB Presentation, Washington D.C., June 13-14, 2001, 2001

 File — Box: 2, Folder: 60
Scope and Contents From the Series:

This series documents the early development process of the Wildlife Disease Research Building up to the point where the redesign began. It is a total of 12.7 Linear Feet. Includes correspondence, pre-construction floor plans and revisions, and design team meeting details.

Dates: 2001